Question: In crashing a project, we routinely focus on those activities that lie on the critical path, not activities with slack time. Explain why this is
In crashing a project, we routinely focus on those activities that lie on the critical path, not activities with slack time. Explain why this is the case.
Step by Step Solution
3.36 Rating (162 Votes )
There are 3 Steps involved in it
The critical path is the longest path through the network Crashing activities on the cr... View full answer