Question: Jack Kanet Manufacturing produces custom-built pollution control devices for medium.-size steel mills. The most recent project undertaken by Jack requires 14 different activities. (a) Jacks

Jack Kanet Manufacturing produces custom-built pollution control devices for medium.-size steel mills. The most recent project undertaken by Jack requires 14 different activities.
(a) Jack€™s managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table.

Jack Kanet Manufacturing produces custom-built pollution control

(b) What is the probability of being done in 53 days?
(c) What date results in a 99% probability ofcompletion?

Most Immediate Optinmistic Likely Pessimistic Activity PredecessorsTime Time Time B, C 18 E, F G, H L, M

Step by Step Solution

3.34 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Jack Kanet Manufacturing produces custom a Activity a m b Expected Time Variance A 4 6 7 583 025 B 1 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

256-B-M-L-O-M (1396).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!