Question: In the following table, project activities in days are listed with three time estimates for duration in days and predecessors for the activities. (a) Calculate

In the following table, project activities in days are listed with three time estimates for duration in days and predecessors for the activities.


In the following table, project activities in days are listed


(a) Calculate the expected time of each activity using MSP.
(b) Construct a Gantt chart using MSP.
(c) Use MSP to draw a network diagram.
(d) Assuming the default 5-day workweek, calculate the critical path of the project.
(e) Calculate the slack for theactivities.

Most Optinistic Likely Pessimistic Tiine Activity Time e Time TimePredecessors 12 10 19 12 18 10 12 14 a, b c, d b, e 12

Step by Step Solution

3.38 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The Pert Entry Form in Microsoft Project is used to enter the three durations After they are in the ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

84-B-M-L-P-M (471).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!