In the following table, project activities in days are listed with three time estimates for duration in
Question:
In the following table, project activities in days are listed with three time estimates for duration in days and predecessors for the activities.
(a) Calculate the expected time of each activity using MSP.
(b) Construct a Gantt chart using MSP.
(c) Use MSP to draw a network diagram.
(d) Assuming the default 5-day workweek, calculate the critical path of the project.
(e) Calculate the slack for theactivities.
Transcribed Image Text:
Most Optinistic Likely Pessimistic Tiine Activity Time e Time TimePredecessors 12 10 19 12 18 10 12 14 a, b c, d b, e 12
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 56% (16 reviews)
The Pert Entry Form in Microsoft Project is used to enter the three durations After they are in the ...View the full answer
Answered By
Muhammad Ahtsham Shabbir
I am a professional freelance writer with more than 7 years’ experience in academic writing. I have a Bachelor`s Degree in Commerce and Master's Degree in Computer Science. I can provide my services in various subjects.
I have professional excellent skills in Microsoft ® Office packages such as Microsoft ® Word, Microsoft ® Excel, and Microsoft ® PowerPoint. Moreover, I have excellent research skills and outstanding analytical and critical thinking skills; a combination that I apply in every paper I handle.
I am conversant with the various citation styles, among them; APA, MLA, Chicago, Havard, and AMA. I also strive to deliver the best to my clients and in a timely manner.My work is always 100% original. I honestly understand the concern of plagiarism and its consequences. As such, I ensure that I check the assignment for any plagiarism before submission.
4.80+
392+ Reviews
587+ Question Solved
Related Book For
Project Management A Managerial Approach
ISBN: 978-0470226216
7th Edition
Authors: Jack R. Meredith, Samuel J. Mantel,
Question Posted:
Students also viewed these Management Leadership questions
-
Construct a network from the information in the following table and identify all the paths in the network, compute the length of each, and indicate the criticalpath. Activity Activity Predecessor...
-
For a major university, match each cost in the following table with the activity base most appropriate to it. An activity base may be used more than once, or not used atall. Activity Base: a. Number...
-
Use the data in the following table to a. Prepare a frequency distribution of the respondents ages b. Cross-tabulate the respondents genders with cola preference c. Identify anyoutliers Weekly Unit...
-
If a quantity is measured to be Q and its exact value is A, then the relative error in Q is If the exact value is A = 35 and you want the relative error in Q to be less than or equal to 0.02 (or 2%),...
-
L'Oréal reports the following income statement accounts for the year ended December 31, 2014 (euros in millions). Prepare the income statement for this company for the year ended December 31,...
-
In Problems 5166, find each indicated quantity if it exists. Let f(x) = (1-x [1 + x (A) lim f(x) x-0 (C) lim f(x) if x 0 if x > 0 . Find (B) lim f(x) x-0 (D) f(0)
-
Show that $\operatorname{Var}(\hat{\mathbf{y}})=\sigma^{2} \mathbf{H}$.
-
Suppose Alexandra Pater, the manager of the Food and Lodging Division at Winter Wonderland Resort, has hired you as a consultant to help her examine her division's performance under several different...
-
How do ethical leaders navigate ethical gray areas and conflicting stakeholder interests while upholding ethical standards and ensuring the long-term sustainability and reputation of the organization...
-
Dynamic Mattress decides to lease its new mattress stuffing machines rather than buy them. As a result, capital expenditure in the first quarter is reduced by $50 million, but the company must make...
-
In the following table are listed tasks, duration in weeks, and predecessors. (a) Construct a Gantt chart using MSP. (b) Assuming the default 5-day workweek, calculate the critical path of the...
-
The Yankee Chair Company was anxious to get a new model rocking chair onto the market. Past efforts to introduce new models had resulted in frustrating failures. Bret Ricks, president of Yankee...
-
Consider the Sun Gas proposed entry into ecommerce in P1-42A. Smith revises her estimates of the benefits from the new system's lower labour costs. She now thinks the savings will be only $933,000....
-
What does the following output? A. [tire-][wheel-] B. tire-wheel C. None of the above. D. The code does not compile. Set set = new HashSet (); set.add("tire-"); List list = new LinkedList (); Deque...
-
Which functional interface, when filled into the blank, prevents the class from compiling? A. DoubleUnaryOperator B. Function C. IntToLongFunction D. UnaryOperator E. All of the above allow the code...
-
Given the following class, how many lines contain compilation errors? A. None. The code compiles as is. B. One. C. Two. D. Three. E. Four. F. Five. 1: package showtimes; 2: import java.util.*; 3:...
-
Which of the following is not a functional interface in the java.util.function package? (Choose two.) A. DoublePredicate B. LongUnaryOperator C. ShortSupplier D. ToIntBiFunction E. ToStringOperator.
-
Which method reference can replace the lambda on the second line so the output is the same? A. a::contains(b) B. a::contains C. String::contains(b) D. String::contains E. The supplied code does not...
-
For its top managers, Global Travel formats its income statement as follows: Globals relevant range is between sales of $250,000 and $360,000. Requirements 1. Calculate the contribution margin ratio....
-
Solve each equation. x 3 - 6x 2 = -8x
-
An employee database that consolidates payroll, personnel, and job skills master files is referred to as a. Data integration. b. Data sharing. c. Data independence.
-
In the calculation of variance for optimistic and pessimistic activity duration estimates made at the 95 or 90 percent level, the denominator of the fraction that approximates the standard deviation...
-
Explain the difference between a project that has a fixed delivery day and one that has a fixed limit on resource usage. Why might a PM be interested in this difference?
-
When allocating scarce resources to several different projects at the same time, why is it important to make sure that all resource calendars are on the same time base (i.e., hourly, daily, weekly ....
-
Given the info below answer the question Inventory 12/31/25 $60,100 Cost of Goods Sold $221,463 Common Stock 74,510 Selling Expenses 15,783 Retained Earnings 45,810 Administrative Expenses 37,696...
-
Greyson Construction has the following account balances at the end of the e year. Accounts Equipment Accounts payable Salaries expense Common stock Land Notes payable Service revenue Balances $24,500...
-
A. Determine the internal forces at sections C, D1 and D2 2kN/m k 2m C 4m Figure 2 e=0.2m 8kN B D D 2m B. Construct bending moment diagram of the beam shown in figures 15kN 4kN/m B D F E (1) (2)...
Study smarter with the SolutionInn App