In the following table, project activities in days are listed

In the following table, project activities in days are listed with three time estimates for duration in days and predecessors for the activities.


In the following table, project activities in days are listed


(a) Calculate the expected time of each activity using MSP.
(b) Construct a Gantt chart using MSP.
(c) Use MSP to draw a network diagram.
(d) Assuming the default 5-day workweek, calculate the critical path of the project.
(e) Calculate the slack for theactivities.