Question: Jill Nicholas believes there must be a better aggregate plan. She has suggested a hybrid plan, using a permanent workforce of 195 employees and subcontracting
Jill Nicholas believes there must be a better aggregate plan. She has suggested a hybrid plan, using a permanent workforce of 195 employees and subcontracting as needed. Once again, Jill has requested that you provide the following information:
(a) Calculate the regular-time production possible each period given a workforce of 195.
(b) Show what would happen if this plan were implemented.
(c) Calculate the costs associated with this plan.
(d) Evaluate the plan in terms of cost, customer service, operations, and humanresources.
.png)
Problem Data Cost data Regular-time labor cost per hour Overtime labor cost per hour Subcontracting cost per unit (labor onl Holding cost per unit per period Back-order cost per unit per period Hiring cost per employee Firing cost per emplo $10.00 $15.00 $84.00 $10.00 $20.00 $600.00 $450.00 y) Capacity data Beginning workforce Beginning inventory Labor standard per unit Regular time available per period Overtime available per period Subcontracting maximum per perio Subcontracting minimum 210 employees 400 units 6 hours 160 hours 32 hours 1000 units 500 units riod Demand data Period1 Period 2 Period 3 Period 4 Period5 Period 6 6000 units 4800 units 7840 units 5200 units 6560 units 3600 units
Step by Step Solution
3.53 Rating (163 Votes )
There are 3 Steps involved in it
a Regulartime production units possible each period given a workforce of 195 160 hoursemployeeperiod6 hoursunit 2667 unitsemployeeperiod ... View full answer