Question: Jobs processed through Percys machine shop pass through three operations: milling, grinding, and turning. The hours required for each of these operations is as follows:
.png)
Sequence the job by
(a) FCFS
(b) Shortest processing time (SPT).
Make a Gantt chart for each machine and each rule. Which sequencing rule would yourecommend?
A e anle Grinding Turning Job
Step by Step Solution
3.21 Rating (168 Votes )
There are 3 Steps involved in it
a FCFS b SPT Recommendation Us... View full answer