Question: Joe thinks that it is probably more efficient to use SPT (shortest processing time) as his priority rule. (a) Develop a sequence using SPT based
(a) Develop a sequence using SPT based on processing time for the wash and dry operation.
(b) Calculate the makespan, the mean job flow time, and the average number of jobs in the system.
Step by Step Solution
3.22 Rating (171 Votes )
There are 3 Steps involved in it
a Makespan 27 hours Mean job flow time 5 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
194-B-M-L-O-M (2787).docx
120 KBs Word File