Long-Term Contract with Interim Loss On March 1, 2010, Pechstein Construction Company contracted to construct a factory

Question:

Long-Term Contract with Interim Loss On March 1, 2010, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2012. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2010, 2011, and 2012 are given below.

image

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2010, 2011, and 2012. (Ignore income taxes.)

(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2010, 2011, and 2012. (Ignore incomestaxes.)

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting

ISBN: 978-0470423684

13th Edition

Authors: Donald E. Kieso, Jerry J. Weygandt, And Terry D. Warfield

Question Posted: