Mrs. Tolstoy and her husband, Serge, are planning their dream house. The lot for the house sits
Question:
The following average cost information is available from a local bank that makes loans to local contractors and disperses progress payments to contractors when specific tasks are verified as complete.
24% ..... Excavation and framing complete
8% ...... Roof and fireplace complete
3% ..... Wiring roughed in
6% ..... Plumbing roughed in
5% ..... Siding on
17% ..... Windows, insulation, walks, plaster, and garage complete
9% ..... Furnace installed
4% ..... Plumbing fixtures installed
10% ..... Exterior paint, light fixtures installed, finish hardware installed
6% ..... Carpet and trim installed
4% ..... Interior decorating
4% ..... Floors laid and finished
a. What is the estimated cost for the Tolstoy’s house if they use contractors to complete all of the house?
b. Estimate what the cost of the house would be if the Tolstoys use their talents to do some of the work themselves.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray
Question Posted: