Question: Network Diagramming Activity Predecessor Duration A START 2 B A 5 C A 6 D B 9 E B, C 3 F D, E 4
Network Diagramming Activity Predecessor Duration A START 2 B A 5 C A 6 D B 9 E B, C 3 F D, E 4 What are the paths? What is the critical path? What is the near critical path? Which activities have float? How much?
Step by Step Solution
3.33 Rating (162 Votes )
There are 3 Steps involved in it
Paths along with duration are i ABDF 2 ii ABEF1 iii ACEF 15 Cirtical path ... View full answer