Question: Activity Predecessor Duration A NONE 2 B A 4 C A 3 D A 2 E B 3 F C 6 G C , D

Activity Predecessor Duration
A NONE 2
B A 4
C A 3
D A 2
E B 3
F C 6
G C,D 5
H E,F 6
I G 5
J H,I 5
Part A
Draw a project network diagram from the above information.
Activities B and H can be shortened to a minimum of 2 weeks; which activity would you shorten to reduce the project duration by 2 weeks?
Why?
Explain the risk associated with leveling resources, compressing or crashing projects, and imposed duration(s) or "catch-up" as the project is being implemented.Activity Predecessor Duration
A NONE 2
B A 4
C A 3
D A 2
E B 3
F C 6
G C,D 5
H E,F 6
I G 5
J H,I 5
Part A
Draw a project network diagram from the above information.
Activities B and H can be shortened to a minimum of 2 weeks; which activity would you shorten to reduce the project duration by 2 weeks?
Why?
Explain the risk associated with leveling resources, compressing or crashing projects, and imposed duration(s) or "catch-up" as the project is being implemented.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!