Question: Given the following project Immediate Activity Predecessor Time (wks) A - 2 B A 5 C A 6 - D B. 4 E C 5
Given the following project
Immediate
Activity Predecessor Time (wks)
A - 2
B A 5
C A 6 -
D B. 4
E C 5
F D,E 4
G F 7
Draw the diagram and determine the ES, EF, LS, and LF, slack and critical path. You will need this information for the questions.
How long will the project take?
What is the ES, EF, LS and LF for activities D and F?
What activities have slack and how much slack do they have?
What is the critical path?