Now suppose the lead time for item A2, shown in problem 6, is three weeks rather than

Question:

Now suppose the lead time for item A2, shown in problem 6, is three weeks rather than two weeks. Based on this information, can the company support the current gross requirements for the A2? Why? What are the implications of having reliable supplier and manufacturing lead times in an MRP environment?