Question: On June 1, 2011, bids were submitted for a construction project to build a new municipal building and fire station. The lowest bid was $5,130,000,

On June 1, 2011, bids were submitted for a construction project to build a new municipal building and fire station. The lowest bid was $5,130,000, submitted by the Shannon Construction Company. Shannon was awarded the contract. Shannon uses the completed-contract method to report gross profit. The following data are given to summarize the activities on this contract for 2011 and 2012. Give the entries to record these transactions using the completed-contractmethod.

On June 1, 2011, bids were submitted for a construction

Estimated Cost to Complete Billings on Contract Collections of Billings Year 2011 2012 Cost Incurred $1.930,000 2.290,000 $2,100,000 3.030,000 $2,420,000 $1,800,000 3,330,000

Step by Step Solution

3.39 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

2011 2012 Construction in Progress 1930000 2290000 Materials Labo... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

92-B-A-R-R (257).docx

120 KBs Word File

Students Have Also Explored These Related Accounting Questions!