Question: On March 1, 2008, bids were submitted for a construction project to build a new municipal building and fire station. The lowest bid was $4,270,000,
On March 1, 2008, bids were submitted for a construction project to build a new municipal building and fire station. The lowest bid was $4,270,000, submitted by the Harper Construction Company. Harper was awarded the contract. Harper uses the completed contract method to report gross profit. The following data are given to summarize the activities on this contract for 2008 and 2009. Give the entries to record these transactions using the completed-contractmethod.
.png)
Cost Estimated Cost Billings on Collections of Year Incurred to Complete Contract Billings 2008 2009 $1,790,000 2,090,000 $1,050.000 3.220.000 $2.140,000 $1.750,000 2,520,000
Step by Step Solution
3.48 Rating (164 Votes )
There are 3 Steps involved in it
2008 2009 Construction in Progress 1790000 2090000 Materials Lab... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
105-B-A-R-R (305).docx
120 KBs Word File