Question: Product P is composed of three subassemblies: K, L, and W. Subassembly K is assembled using 3 Gs and 4 Hs; L is made of
Product P is composed of three subassemblies: K, L, and W. Subassembly K is assembled using 3 Gs and 4 Hs; L is made of 2 Ms and 2 Ns; and W is made of 3 Zs. On-hand inventories are 40 Gs, and 200 Hs. Scheduled receipts are 10 Ks at the start of week 3 and 30 Ks at the start of week 6.
One hundred Ps must be shipped at the start of week 6, and another 100 at the start of week 7. Manufacturing lead times are two weeks for subassemblies and purchase lead times are one week for the components. Final assembly of P requires one week for 100 units. Include an extra 10-percent scrap allowance in each planned order of G. The minimum order size for H is 200 units. For other items, use lot-for-lot ordering. Develop each of the following:
a. Tire product structure tree.
b. The material requirements plan for P, K, G, and H.
One hundred Ps must be shipped at the start of week 6, and another 100 at the start of week 7. Manufacturing lead times are two weeks for subassemblies and purchase lead times are one week for the components. Final assembly of P requires one week for 100 units. Include an extra 10-percent scrap allowance in each planned order of G. The minimum order size for H is 200 units. For other items, use lot-for-lot ordering. Develop each of the following:
a. Tire product structure tree.
b. The material requirements plan for P, K, G, and H.
Step by Step Solution
★★★★★
3.40 Rating (163 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
a Product Structure Tree b Production Schedule Weeks Beg Inv 1 2 3 4 5 6 7 Quantity 100 100 P LT ... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
Document Format (1 attachment)
686-B-M-L-O-M (5195).docx
120 KBs Word File