Question: Eighty units of product E are needed at the beginning of week 6. Three cases (30 units per case) of J have been ordered and
Eighty units of product E are needed at the beginning of week 6. Three cases (30 units per case) of J have been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5. Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B and 20 units of J on hand now. Manufacturing lead times are two weeks each for E and B, and purchase lead time is one week for J.
.png)
a. Prepare the materiel requirements plan for component J.
b. Suppose that now is week 4 and the quantity of E needed in week 6 has changed from 80 to 70. The planned order releases through week 3 and scheduled receipts have all been executed as in part α. How many more (relative to part a) Bs and Js will be on Land in week 6?
B(2) J13) J(4 F2)
Step by Step Solution
3.37 Rating (166 Votes )
There are 3 Steps involved in it
a Production Schedule Week Beg Inv 1 2 3 4 5 6 Quantity 80 ELT 2 wks Beg Inv 1 2 3 4 5 6 Gross requi... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
686-B-M-L-O-M (5194).docx