Rain is falling on a poorly designed 150-m2 flat roof of a contemporary home. The design flaw

Question:

Rain is falling on a poorly designed 150-m2 flat roof of a contemporary home. The design flaw requires the water level on the roof to reach approximately 5 cm above the plane of the roof before the water flows into drains.
(a) Taking the accumulated rain on the roof as the system, can the process before the water level reaches 5 cm be considered batch, semi-batch, or continuous? Is it transient or steady-state? Once the water starts to flow into the drains, how do your answers change?
(b) Before the water starts draining, which of the terms in the general balance equation (Equation 4.2-1) can be omitted? Why? How do your responses change after water starts draining?
(c) Water begins flowing from the roof after 30 minutes of rainfall. What will the rate of draining (L/s) be if rain continues to fall at the same rate?
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Elementary Principles of Chemical Processes

ISBN: 978-1119498759

4th edition

Authors: Richard M. Felder, ‎ Ronald W. Rousseau, ‎ Lisa G. Bullard

Question Posted: