Question: Reconfigure the network in Figure 11.21 using the critical chain approach. Remember to reconfigure the activities to late start where appropriate. What is the original
Reconfigure the network in Figure 11.21 using the critical chain approach. Remember to reconfigure the activities to late start where appropriate. What is the original critical path? What is the original project duration? How much feeder buffer should be applied to the noncritical paths? What is the length of the project buffer? Assume the 50% likelihood is exactly half the duration of current project activities.
.png)
B (10) C(15) D (8) E (10) H (15) F (18) G(15)
Step by Step Solution
3.22 Rating (166 Votes )
There are 3 Steps involved in it
The noncritical paths are activities D and E with 19 days ... View full answer