Question: Refer to Example 4. Find the optimal solution, i.e., the sequence of jobs that satisfies the due hours (i.e., end of the 8th hour) for
Refer to Example 4. Find the optimal solution, i.e., the sequence of jobs that satisfies the due hours (i.e., end of the 8th hour) for all five jobs.
Job 1 Job 2 Job 3 Job 4 Job 5 1. Drill 1 Lathe 2 Grind 2 Drill Mill 2. Lathe 2 Mill 2 Drill Grind 2 Drill 3. Grind Grind Mill 2 Lathe Lathe 4. Mill 2 Drill 2 Lathe 2 Grind Total (hours) 6 8 5
Step by Step Solution
3.48 Rating (161 Votes )
There are 3 Steps involved in it
Switch job 4 and 5 in the MST seq... View full answer