Processing Due Date Job Time (days (days) 20 18 25 17 9
Step by Step Solution
3.46 Rating (166 Votes )
There are 3 Steps involved in it
a Time Due Job days Date Slack Critical Ratio A 8 20 12 20 8 25 B 10 18 8 18 10 18 C 5 25 20 25 5 50 ... View full answer