Question: Refer to Problem 7.5. If a contract for the second and third years is pending, what are the implications for process selection? In problem 7.5,

Refer to Problem 7.5. If a contract for the second and third years is pending, what are the implications for process selection?

In problem 7.5, Meile Machine Shop, Inc., has a 1-year contract for the production of 200,000 gear housings for a new off-road vehicle. Owner Larry Meile hopes the contract will be extended and the volume increased next year. Meile has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM).

The cost data follow:


Refer to Problem 7.5. If a contract for the second




Which process is best for this contract?

General- Flexible Purpose Manufacturing Dedicated (FMS) 200,000 Equipment Systm Machine (GPE) (DM) Annual contracted units Annual fixed cost Per unit variable 200,000 $100,000 200,000 $200,000 $500,000 cost 15.00 14.0013.00

Step by Step Solution

3.52 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The optimum process will change at 100000 units and 300000 units as shown ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

256-B-M-L-O-M (1605).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!