Question: Set up a spreadsheet to solve Problem 2. Determine the estimated cost of the work performed each week given the taskswith their associated costs and

Set up a spreadsheet to solve Problem 2.

Determine the estimated cost of the work performed each week given the tasks—with their associated costs and schedules—shown in the following table.


Set up a spreadsheet to solve Problem 2. Determine the


When a task spans more than one week, the costs should be divided equally among theweeks.

WEEK COST ($) 2,200 19,600 TASK START FINISH Excavation Footings and Foundation Waterproofing Backfill and Under Slab Gravel Slab on Grade Masonry Structural Steel Joist and Deck Hollow Metal Doors and Hardware Overhead Doors Skylights Roof Insulation Membrane Roofing Heating Electrical Cleanup 900 2,000 22,300 54,000 2,400 11,900 2,100 10,100 5,800 5,600 13,000 15,600 29,800 1,000 4 4 8 8 9 9 10 10 10 10 12 12 12

Step by Step Solution

3.40 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Task Cost Dur Start Finish Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Excel file Icon

246-B-F-F-M (1851).xlsx

300 KBs Excel File

Students Have Also Explored These Related Finance Questions!