Question: Shirley Hopkins is developing a program in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a
.png)
(a) Develop an AON network for this problem.
(b) What is the critical path?
(c) What is the total project completion time?
(d) What is the slack time for each individualactivity?
Immediate Activity Predecessor(s) Time days) 10 A, D E, F
Step by Step Solution
3.39 Rating (174 Votes )
There are 3 Steps involved in it
a b Critical path is BDEG c Total project takes 26 da... View full answer