Question: Stephen Hall is developing a program in supply chain management certification for managers. Hall has listed a number of activities that must be completed before
.png)
a) Develop an AON network for this problem.
b) What is the critical path?
c) What is the total project completion time?
d) What is the slack time for each individualactivity?
IMMEDIATE ACTIVITY | PREDECESSORS) I TIME(DAYS) 10 A D E, F
Step by Step Solution
3.38 Rating (167 Votes )
There are 3 Steps involved in it
a b Critical path is BDEG d Activity Time ES EF ... View full answer