Shown below are the planning periods demand and the standard hours required for four products from a

Question:

Shown below are the planning period€™s demand and the standard hours required for four products from a company€™s sales and operations plan. Assuming that the company has 65,000 hours of labor available during the planning period, determine whether the sales and operations plan is feasible.