A process that is being considered for construction has been through several technical reviews; block flow, process

Question:

A process that is being considered for construction has been through several technical reviews; block flow, process flow, and piping and instrumentation diagrams are available for the process. Explain the changes that would have to be made to the three principal diagrams if during a final preconstruction review, the following changes were made:

  • The efficiency of a fired heater had been specified incorrectly as 92% instead of 82%.
  • A waste process stream flowrate (sent to a sludge pond) was calculated incorrectly and is now 30% greater than before.
  • It has been decided to add a second (backup) drive for an existing compressor.
  • The locations of several control valves have changed to allow for better operator access.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Analysis Synthesis And Design Of Chemical Processes

ISBN: 9780134177403

5th Edition

Authors: Richard Turton, Joseph Shaeiwitz, Debangsu Bhattacharyya, Wallace Whiting

Question Posted: