Four products (A-D) are made in a batch processing plant. The times (in hours) required for each

Question:

Four products (A-D) are made in a batch processing plant. The times (in hours) required for each piece of equipment for each product are shown in Table P3.22.Table P3.22 Equipment Processing Times for Problem 3.22 Product Mixer/Heater Reactor Filter Crystallizer

Using this information, answer the following questions. Note that you do not have to draw a Gantt chart to answer any of these questions. Note that all products use the equipment in the same order unless that equipment is not used.

  • Over a 600 h period (approximately 1 month), the required number of batches for products B and D is 15 and 10, respectively.
  • The demand for products A and C is such that three times as many batches of A compared to C are required. Determine how many batches of A can be manufactured if single-product campaigns are used. In this problem, you should use the exact cycle time expression for each product.
  • Repeat Part (b) but use the limiting cycle time for each product.
  • For a process with unlimited intermediate storage (uis process) and an equal number of batches for each product, determine the maximum number of batches for each product using a mixed product campaign (ABCDABCD… or ACBDACBD…, etc.) in a 600 h operating period.

Step by Step Answer:

Related Book For  answer-question

Analysis Synthesis And Design Of Chemical Processes

ISBN: 9780134177403

5th Edition

Authors: Richard Turton, Joseph Shaeiwitz, Debangsu Bhattacharyya, Wallace Whiting

Question Posted: