Question: Consider the hardness measurement data in Exercise 15-19. Set up a CUSUM scheme for this process using = 50 and = 2 so

Consider the hardness measurement data in Exercise 15-19. Set up a CUSUM scheme for this process using μ = 50 and σ = 2 so that K = 1 and H = 10. Is the process in control?


Exercise 15-19

Twenty successive hardness measurements are made on a metal alloy, and the data are shown in the following table.

Hardness Observation 11 12 Observation Hardness 51 51 57 52 3 4

Hardness Observation 11 12 Observation Hardness 51 51 57 52 3 4 58 50 54 55 55 13 14 15 53

Step by Step Solution

3.29 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The process is not in control K k 1 ... View full answer