Question: As in Exercise 65, a crew of workers is constructing a tunnel. The time required to dig 100 m increases by 10% each week, starting
As in Exercise 65, a crew of workers is constructing a tunnel. The time required to dig 100 m increases by 10% each week, starting with 1 week to dig the first 100 m. Can the crew complete a 1.5-km (1500-m) tunnel in 30 weeks? Explain.
Data from Exercise 65
A crew of workers is constructing a tunnel through a mountain. Understandably, the rate of construction decreases because rocks and earth must be removed a greater distance as the tunnel gets longer. Suppose that each week the crew digs 0.95 of the distance it dug the previous week. In the first week, the crew constructed 100 m of tunnel.
Step by Step Solution
3.51 Rating (161 Votes )
There are 3 Steps involved in it
tn Let to be the time required to dig mete... View full answer