Question: A contractor has a contract to remove and replace the existing landscape and sidewalks around an office building. The work includes demolition of the existing
A contractor has a contract to remove and replace the existing landscape and sidewalks around an office building. The work includes demolition of the existing landscaping and sidewalks, importing fill and grading around the office building, constructing new concrete sidewalks, and new landscaping. The contractor uses the cost codes in Figure 2-6. The contractor will perform all of the work except placing the site concrete and the landscaping. The original estimate for the demolition was $30,000 and a $5,000 change order has been approved to remove some unexpected debris found during the demolition. The demolition work has been completed at a cost of $33,562. The original estimate for the fill and grading was $17,500 and a $2,000 change order for importing additional fill to replace the debris has been approved. The fill and grading costs to date are $17,264 and the cost to complete has been estimated at $2,236. The original budget for the labor to pour the concrete was $19,200 and no changes have been made. The concrete labor has been subcontracted out for $19,200, for which the contractor has received a bill for $15,200. The original budget for the concrete for the sidewalks was $9,900 and no changes have been made. The contractor has spent $7,425 for concrete and estimates that $1,950 of concrete will be needed to complete the project. The original estimate for the landscaping was $37,500 and no changes have been made. The landscape work has been subcontracted out for $37,500. The landscaping work has yet to start and no bills have been received. M Determine the total estimated cost at completion for the project and the variance for each cost code.
In figure 2.6

Code Description 01000 GENERAL REQUIREMENTS 01100 Supervision 01400 General Labor 01600 Temporary Facilities 01700 Temporary Utilities 01800 Temporary Phone 01900 Clean-Up 02000 EXISTING CONDITIONS 02050 050 Demolition 03000 CONCRETE 03200 Under-slab Gravel 03300 Footing & Found.-Labor 03400 Footing & Found.-Conc. 03450 Concrete Pump 03500 Slab/Floor-Labor 03600 Slab/Floor-Concrete 03650 Light-Weight Concrete 03700 Pre-cast Concrete 03900 Rebar 04000 MASONRY 04100 Masonry 05000 METALS 05100 Structural Steel 05300 Joist & Deck 05400 Misc. Steel 05900 Erection 06000 WOOD, PLASTICS, & COMP. 06110 Rough Carpentry 06120 Lumber 06150 Trusses 06210 Finish Carpentry 07000 THERMAL & MOIST. PROT. 07100 07200 Insulation 07210 Foundation Insulation 07250 Fireproofing 07300 Stucco Waterproofing 07400 Siding 07450 Rain Gutters 07500 Roofing 07600 Flashings-Sheet Metal 07700 Roof Specialties 07900 Caulking & Sealants COST CODES 08000 OPENINGS 08110 Metal Doors & Frames 08200 Wood Doors 08300 Overhead Doors 08400 Store Fronts 08700 Hardware 08800 Glass & Glazing Code Description 09000 FINISHES 09050 Metal Studs 09100 Drywall 09200 Ceramic Tile 09300 Acoustical Treatment Carpet & Vinyl 09400 09800 Paint 09850 Wall Coverings 10000 SPECIALTIES 10400 Signage 10700 Toilet Partitions 10800 Toilet & Bath Accessories 11000 EQUIPMENT 11100 Appliances 12000 FURNISHINGS 12300 Cabinetry & Counter Tops 12350 Counter Tops 12500 Window Treatments 14000 CONVEYING SYSTEMS 14100 Elevators 20000 FIRE SUPPRESSION 21100 Fire Sprinklers 22000 PLUMBING 22100 Plumbing 23000 HVAC 23100 HVAC 23200 Gas Lines 26000 ELECTRICAL 26100 Electrical 31000 EARTHWORK 31100 Grading & Excavation. 32000 EXTERIOR IMPROVEMENTS 32100 Asphalt 32200 Site Conc.-Labor 32300 Site Conc.-Concrete 32400 Signage 32500 Landscaping 32550 Fencing 32600 Dumpster Enclosures 32900 Outside Lighting 33000 UTILITIES 33100 Sanitary Sewer 33200 Water Line 33300 Storm Drain 33400 Gas Lines 33500 Power Lines 33600 Telephone Lines
Step by Step Solution
3.46 Rating (182 Votes )
There are 3 Steps involved in it
The demolition numbers are as follows Original Estimate 30000 Change Orders 5000 Total Estimate 30000 5000 35000 Committed Costs 0 Committed Costs Invoiced 0 The Noncommitted Costs Invoiced 33562 Tota... View full answer
Get step-by-step solutions from verified subject matter experts