Question: A project is being managed by a project manager. A large portion of the work of the project is being subcontracted to an outside vendor.
A project is being managed by a project manager. A large portion of the work of the project is being subcontracted to an outside vendor. During the project it is found that a significant change in the design of the project is necessary. The project manager should:
a. Issue a change notice to the contractor immediately.
b. Issue a purchase order to investigate the change.
c. Notify the contractor of the design change possibility.
d. Rebid the contract.