Question: A project manager facilitates the voting process for decision-makers who have convened to review a major deliverable that has been completed. The intent of the
A project manager facilitates the voting process for decision-makers who have convened to review a major deliverable that has been completed. The intent of the meeting is to vote on whether to approve and accept the deliverable. What key input will the committee need to reference to vote?
A. Deliverables B. Accepted deliverables C. Verified deliverables D. Work performance information