Question: Using the earned-value analysis technique, a project manager calculates a schedule performance index of 0.75 and a cost performance index of 1.25. To bring the

Using the earned-value analysis technique, a project manager calculates a schedule performance index of 0.75 and a cost performance index of 1.25. To bring the schedule back on track, the project manager decides to allocate additional resources to critical activities in order to complete them faster. What technique are they using to control the schedule?

A. Fast tracking B. Leads and lags C. Crashing D. Resource optimization