Question: A project manager has structured his project in a way that will allow for the planning of the project to occur during the early phases
A project manager has structured his project in a way that will allow for the planning of the project to occur during the early phases of the life cycle, with minimal changes thereafter. This approach is associated with which development life cycle?
A. Iterative B. Predictive C. Adaptive D. Incremental