Question: A project manager is currently working on a pharmaceutical project. The activities that will produce the deliverables of Phase 1 are currently being planned out

A project manager is currently working on a pharmaceutical project. The activities that will produce the deliverables of Phase 1 are currently being planned out in detail. All other work will be planned out at higher levels until additional product details are known through testing results. This strategy is known as:

A. Rolling wave planning B. Progressive elaboration C. Scope creep D. Initiating