Question: A project manager is dealing with risk analysis on a software development project. There is a risk that the module that creates the most important

A project manager is dealing with risk analysis on a software development project. There is a risk that the module that creates the most important report that the system will create will not work properly and will require 200 person-hours to correct. The project manager decides to do nothing about this risk. Which of the following risk strategies is the project manager employing?

a. Acceptance

b. Avoidance

c. Mitigation

d. Deflection