Question: When using PERT analysis on a project schedule, probabilistic or expected durations are used for activity durations. If there is a concern that the critical
When using PERT analysis on a project schedule, probabilistic or expected durations are used for activity durations. If there is a concern that the critical path may shift due to durations changing within the expected range, what technique can be used?
a. CPM
b. Monte Carlo
c. Decision trees
d. Finite element analysis