Question: A project manager is running a software project that is supposed to be delivered in phases. She was planning on dividing the resources into two
A project manager is running a software project that is supposed to be delivered in phases. She was planning on dividing the resources into two separate teams to do the work for two phases at the same time, but one of her senior developers suggested that she use an Agile methodology instead, and she agrees. Which of the following BEST describes the relationship between her project’s phases?
A. Sequential relationship B. Iterative relationship C. Constrained relationship D. Overlapping relationship