Question: A project manager is using a histogram to analyze defects found by the team during inspection activities. What process is being performed? A. Plan Quality
A project manager is using a histogram to analyze defects found by the team during inspection activities. What process is being performed?
A. Plan Quality B. Perform Quality Control C. Perform Quality Assurance D. Verify Scope