Question: 2. A project manager is using a histogram to analyze defects found by the team during inspection activities. What process is being performed? A. Quality
2. A project manager is using a histogram to analyze defects found by the team during inspection activities. What process is being performed? A. Quality Planning B. Perform Quality Control C. Perform Quality Assurance D. Scope Verification