Question: An important part of performing stakeholder analysis is documenting quantifiable expectations. Which of the following expectations is quantifiable? A. The project must improve customer satisfaction
An important part of performing stakeholder analysis is documenting quantifiable expectations. Which of the following expectations is quantifiable?
A. The project must improve customer satisfaction B. The project should be higher quality C. The project must yield a 15% reduction in part cost D. All stakeholders’ needs must be satisfied