Question: Brandi is a project manager on a software project. About halfway through development, her team found that they had not estimated enough time for some
Brandi is a project manager on a software project. About halfway through development, her team found that they had not estimated enough time for some of the technical work they needed to do. She requested that the new work be added to the scope statement and that the time to do the work be added to the schedule. The change control board approved her change. What’s her next step?
A. Update the scope and schedule baselines to reflect the approved change B. Start doing the work C. Gather performance metrics on the team’s work so far D. Perform Quality Assurance