Question: Develop an integer programming model for the resource allocation problem in Figure 7.47, assuming that daily resource availability is 5 units. Use LINDO or any
Develop an integer programming model for the resource allocation problem in Figure 7.47, assuming that daily resource availability is 5 units. Use LINDO or any other integer programming software to determine an optimal solution to your model. Discuss the results. Draw the project schedule chart (Gantt chart).
Figure 7.47

(5-3) (2-2) (4-2) 2 (duration-daily resource requirement) 3 (2-4) (1-2) 5