Question: Solve Exercise 7.14 (integer programming) using the simulated annealing procedure. Use (T=60, k=0.8) and stop when the order does not change in three iterations. Exercise

Solve Exercise 7.14 (integer programming) using the simulated annealing procedure. Use \(T=60, k=0.8\) and stop when the order does not change in three iterations.

Exercise 7.14

Develop an integer programming model for the resource allocation problem in Figure 7.47, assuming that daily resource availability is 5 units. Use LINDO or any other integer programming software to determine an optimal solution to your model. Discuss the results. Draw the project schedule chart (Gantt chart).

Figure 7.47

(5-3) (2-2) (4-2) 2 (duration-daily resource requirement) 3 (2-4) (1-2) 5

(5-3) (2-2) (4-2) 2 (duration-daily resource requirement) 3 (2-4) (1-2) 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!