Question: Develop the precedence diagram network for the following project and then calculate the TF and FF for each activity. Mark critical activities with an asterisk.

Develop the precedence diagram network for the following project and then calculate the TF and FF for each activity. Mark critical activities with an asterisk.

Activity a b C d e f 8 h j k Duration

Activity a b C d e f 8 h j k Duration 22 10 13 8 15 17 15 6 11 12 20 Immediately Following Activities d.j cf d.j c.f.g h,i,k h,i,k d.j j