Question: Molly is the lead project manager for Cube Systems Plus. A project that she is managing is utilizing three different vendors to perform various components

Molly is the lead project manager for Cube Systems Plus. A project that she is managing is utilizing three different vendors to perform various components of work. Molly’s customer has just requested that the delivery date be pushed up by one month. To determine whether this is possible, she sits down with the account managers of the three vendor companies to discuss availability. Where will Molly and the account managers look to view resource availability?

A. Resource management plan B. Seller Gantt charts C. Contract D. Resource calendars