Question: Suppose two serial activities A and B are the only activities in a precedence diagramming network. Activity A precedes activity B. There is an SS
Suppose two serial activities A and B are the only activities in a precedence diagramming network. Activity A precedes activity B. There is an SS restriction of 4 time units and an FF restriction of 3 time units between A and B.
a. Determine the mathematical relationship between the duration of \(A\left(t_{A}\right)\) and the duration of \(B\left(t_{B}\right)\).
b. Verify your response to part (a) by considering the following alternate cases:
Case 1: \(t_{A}=0\)
Case 2: \(0 Case 3: \(1 Case 4: \(t_{A}=4\) Case 5: \(t_{A}>4\)
Step by Step Solution
3.39 Rating (155 Votes )
There are 3 Steps involved in it