Question: The key inputs to activity definition are: a. Work breakdown structure, the project schedule, and the network diagram. b. Project schedule, progress reports, and change
The key inputs to activity definition are:
a. Work breakdown structure, the project schedule, and the network diagram.
b. Project schedule, progress reports, and change requests.
c. The project network diagram, constraints, and durations.
d. The work breakdown structure, the scope statement, and historical information that supports the applicable activity.