Question: Inputs to activity definition include: A. Work breakdown structure, project schedule, and network diagram. B. Project schedule, progress reports, and change requests. C. Project network

Inputs to activity definition include: A. Work breakdown structure, project schedule, and network diagram. B. Project schedule, progress reports, and change requests. C. Project network diagram, constraints, and durations. D. Project scope statement, work breakdown structure, and project management plan.