Question: Using the computational approach presented in this chapter, compute the scaled CAF weight for each activity in Exercise 5.3. Exercise 5.3 Use the minimum totals

Using the computational approach presented in this chapter, compute the scaled CAF weight for each activity in Exercise 5.3.

Exercise 5.3

Use the minimum totals lack (Min TS) heuristic to schedule the resource-constrained project. If a tie occurs, use minimum activity duration to break the tie.

Units of resource type 1 available \(=10\)

Units of resource type 2 available \(=15\)

Resource Units Activity Predecessor a M b Type 1 Type 2 A

Resource Units Activity Predecessor a M b Type 1 Type 2 A 1 2 B 5 9 47 4 3 0 7 5 4 C 2 4 10 5 4 1 DEFC A 1 3. C 4 5 +7 4 2 0 7 A 3 4 G B, D, E 1 2 3 42 53 3 7 19 6 2

Step by Step Solution

3.48 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!