Question: Using the computational approach presented in this chapter, compute the scaled CAF weight for each activity in Exercise 5.3. Exercise 5.3 Use the minimum totals
Using the computational approach presented in this chapter, compute the scaled CAF weight for each activity in Exercise 5.3.
Exercise 5.3
Use the minimum totals lack (Min TS) heuristic to schedule the resource-constrained project. If a tie occurs, use minimum activity duration to break the tie.
Units of resource type 1 available \(=10\)
Units of resource type 2 available \(=15\)

Resource Units Activity Predecessor a M b Type 1 Type 2 A 1 2 B 5 9 47 4 3 0 7 5 4 C 2 4 10 5 4 1 DEFC A 1 3. C 4 5 +7 4 2 0 7 A 3 4 G B, D, E 1 2 3 42 53 3 7 19 6 2